- Client: Etienne Bürcher
- Site management / reference person: Kurt Frey
- Project manager: Erhard Burgener
- Foreman: Hugo Gasser
- Construction period: July 2024 - September 2024
- Construction costs: 500'000.-
Technical data:
- 2'200 m² formwork
- 75 tons of reinforcement
- 600 m³ concrete
Project description:
The Bürcher Etienne suckler cow barn is a three-storey building comprising a ground floor and two basement floors, all of which are accessible at ground level.
The surrounding walls and ceilings of the two basement floors are made of cast concrete, the first floor of timber construction. The access road from the cantonal road to the stables is supported on the sides by rollers and in-situ concrete walls. The surface is asphalted. The spring supply line of the Bachalpe has been replaced over a length of 3 km. The work was completed in a short construction period.