Visp

New DEFH D'Onofrio building

  • Client: D'Onofrio Pierluigi & Antonio
  • Site management / Reference person: D'Onofrio Pierluigi & Antonio
  • Foreman: D'Onofrio Pierluigi
  • Foreman: Elmar Pfammatter
  • Construction period: March 2020 to June 2020

Technical data:

  • 1'200 m³ excavated material
  • 1'300 m² wall formwork
  • 100m² exposed concrete type 3.1 BOK 2
  • 500m² slab formwork
  • 40 tons of reinforcement
  • 400 m³ concrete
  • 200m² brickwork

Project description:

A double detached house in solid construction was built in Visp. Due to large spans and cantilevered components, the formwork removal times had to be extended.

Requirements:

  • Exposed concrete type 3.1 BOK 2 board structure
  • Start of pandemic measures
  • Short construction time
  • Longer stripping times
  • Elaborate basic construction

Contact Persons

Pierluigi D'Onofrio

Head of Pollutant Remediation Department /
Head of Underlayment Flooring Department /
Technician HF / Site Manager SBA

+41 79 368 63 62

+41 27 948 05 48

pierluigi.donofrio@volken-group.ch