Bitsch

Removal of inserts Lot 1

  • Client: Canton of Valais
  • Site management / reference person: Canton of Valais Patrick Stoffel
  • Site manager: Celine Ludi
  • Foreman: Pietro Pratico
  • Construction period: July 2025 - June 2026
  • Construction costs: CHF 2.3 million

Technical data:

  • Excavation / removal 2,800 m3
  • Nail wall 430 m2
  • Anchors 1'165 m
  • Micropiles 120 m'
  • In-situ concrete 380 m3
  • Quarry stone-clad retaining wall 190 m3
  • Unbound mixture 0/45 2'000 m3
  • Pipelines 780 m
  • Retention basin 2 pcs.
  • Inlet and inspection chambers 25 pcs.
  • Surfacing 800 tons

Project description:

The road is being widened to make it easier for trucks and buses to turn and negotiate bends. A leaning structure will be built as a foundation for the widening. The embankment will be secured with a nail wall and anchors and visually enhanced with a quarry stone wall. In addition, pipes, inlet and inspection shafts and a retention basin will be installed and the surface will be resurfaced.

Requirements:

  • During ongoing traffic
  • Tight space conditions