Renovation of Griene Wase springs, Zermatt

  • Client: Municipality of Zermatt, Kirchplatz 3, 3920 Zermatt
  • Site manager/reference person: Paul Schwery / Water supply Zermatt
  • Site manager: Celine Ludi
  • Foreman: Marco Gruber
  • Construction time: September 2024 and October 2024
  • Construction costs: 0.10 million

Technical data:

  • 40.00 m long main trench for drinking water transport pipeline
  • Various outlets to individual springs
  • Spring catchment, 1 piece demolished and carefully rebuilt

Project description:

The existing Griene Wase spring was demolished and rebuilt. The discharge of 40m was also rebuilt.

Requirements:

  • Work near the track
  • Work in spring protection area
  • Working on steep terrain