Renovation of multi-purpose parking deck

  • Client: Municipality of Naters
  • Site management/reference person: Dreipunkt AG, Cyrill Chastonay
  • Site manager: Mathias Wyssen
  • Foreman: Daniel Peixoto
  • Construction period: August 2023 - March 2024
  • Construction costs: 0.4 mio

Technical data:

  • 960 m² pavement demolition
  • 960 m² demolition of concrete pressure distribution slab
  • 240 m² concrete jetting
  • 960 m² shot blasting
  • 240 m² concrete reprofiling

Project description:

The parking deck at the multi-purpose facility in Mund was extensively renovated. The existing surface and the underlying concrete pressure distribution slab were removed. After sealing the hall ceiling, the concrete layer was professionally rebuilt.
At the same time, the hall façade was thoroughly cleaned using a high-pressure jet and then reprofiled to renew its structure and appearance.

Requirements:

  • Hall ceiling can only be driven on with a maximum of 3 tons
  • Very little installation space