Wind and weather also take their toll on mountain roads. That is why experts from the Volken Group, together with a team from Voweg, are currently renovating and widening the forest road and the one-sided turning area at Grimselboden. They are replacing seven existing cross-drains with ten new ones, removing 630 m³ of organic debris, preparing 1,700 m² of subgrade, laying 1,700 m² of geotextile, and excavating 520 m of a V-shaped ditch. What makes this pilot project unique is that the 650 cubic meters of fill material required for it are processed directly at the Engi quarry. Using a mobile crusher that also handles screening and produces material in compliance with standards. Once the surface material has been mixed with lime and moistened, trucks transport all construction materials to the site, where they are then installed, graded, and compacted.