- Client: Municipality of Obergoms
- Site management/reference person: SRP Ingenieur AG
- Site manager: Rafael Millius
- Foreman: Diego Bodenmann
- Construction period: April 2023 - December 2024
- Construction costs: 3.60 million
Technical data:
- Logging and clearing approx. 9'000 m²
- Soil removal & excavation pits approx. 25,000 m³ solid
- Embankment fills approx. 10,000 m³ solid
- Block set shoring approx. 6'000 m³ solid
- Filter and drainage layers approx. 3,500 m³ solid
- Seepage pipes approx. 500 m
- PE pipes approx. 250 m
- Cable protection pipes approx. 400 m
- Geotextiles approx. 15,000 m²
- Nail walls shotcrete approx. 750 m²
- Anchors approx. 120 pieces
- Bridge demolition/new construction 2 pieces
- Formwork approx. 1'100 m²
- Reinforcement approx. 70 tons
- Concrete approx. 500 m³
- Surfacing work approx. 500 m²
- Building demolition 4 pieces
- Culvert structure 4 x DN600, approx. 20 m
Project description:
The Ägene flood protection project in Ulrichen comprises comprehensive structural measures to improve protection against flood events and to enhance the ecological value of the watercourse.
- Dam construction along the right bank of the Ägene / terrain adjustments
- Construction of two bridges (concrete structures); bridge to the campsite & bridge to the hole
- Extension of the Langlauf bridge (left bank)
- Hydraulic engineering design of the banks and estuary area
- Watercourse structuring
- Catchment structures & pipes to secondary channel (Wiesengbach)
- Demolition and dismantling (bridges, buildings, decking, fences and fireplaces)
- Culvert structures
- Construction of an alluvial wood screen
- Surfacing work
- Excavation work and securing
- Miscellaneous ancillary work
Requirements:
- Construction in water & dewatering
- Construction logistics
- Environmental regulations and occupational safety during flooding











