Ulrichen

Cervical spine Ägena

  • Client: Municipality of Obergoms
  • Site management/reference person: SRP Ingenieur AG
  • Site manager: Rafael Millius
  • Foreman: Diego Bodenmann
  • Construction period: April 2023 - December 2024
  • Construction costs: 3.60 million

 

Technical data:

  • Logging and clearing approx. 9'000 m²
  • Soil removal & excavation pits approx. 25,000 m³ solid
  • Embankment fills approx. 10,000 m³ solid
  • Block set shoring approx. 6'000 m³ solid
  • Filter and drainage layers approx. 3,500 m³ solid
  • Seepage pipes approx. 500 m
  • PE pipes approx. 250 m
  • Cable protection pipes approx. 400 m
  • Geotextiles approx. 15,000 m²
  • Nail walls shotcrete approx. 750 m²
  • Anchors approx. 120 pieces
  • Bridge demolition/new construction 2 pieces
  • Formwork approx. 1'100 m²
  • Reinforcement approx. 70 tons
  • Concrete approx. 500 m³
  • Surfacing work approx. 500 m²
  • Building demolition 4 pieces
  • Culvert structure 4 x DN600, approx. 20 m

 

Project description:

The Ägene flood protection project in Ulrichen comprises comprehensive structural measures to improve protection against flood events and to enhance the ecological value of the watercourse.

  • Dam construction along the right bank of the Ägene / terrain adjustments
  • Construction of two bridges (concrete structures); bridge to the campsite & bridge to the hole
  • Extension of the Langlauf bridge (left bank)
  • Hydraulic engineering design of the banks and estuary area
  • Watercourse structuring
  • Catchment structures & pipes to secondary channel (Wiesengbach)
  • Demolition and dismantling (bridges, buildings, decking, fences and fireplaces)
  • Culvert structures
  • Construction of an alluvial wood screen
  • Surfacing work
  • Excavation work and securing
  • Miscellaneous ancillary work

Requirements:

  • Construction in water & dewatering
  • Construction logistics
  • Environmental regulations and occupational safety during flooding