- Client: Canton of Valais
- Construction management / contact person: OBL – DNSB – Daniel Fryand / öBL – DNSB – Ralph Tscherry / Technical management – SBP Ingenieure AG – Simon Murmann
- Construction manager: Jasin Ajeti
- Foreman: Alain Ritz
- Construction period: March to July 2024
- Construction costs: 950,000
Technical data:
- 900 m³ excavation / removal
- 3,300 m³ fill, loading, transport, installation G2
- 2,400 m³ foundation layers UG 0/45
- 4,800 m utility lines
- 4 inspection chambers
- 1,000 tons of pavement
- 10 tons of mastic asphalt
- 720 m² of marl pavement
- 30 m culvert, Spiwell pipe
Project description:
The project for the new Basperstrasse North Canal begins at Bahnhofstrasse in Turtig (North Canal crossing area), runs eastward along the GERA, the pumping station, and the GERA East headquarters, then crosses the North Canal and connects to Lot 30095 at the industrial zone intersection. The road route will partially contain the energy supply for the Raron covered cutting and a cable duct block belonging to the municipality of Raron. The project for the new Basperstrasse Nordkanal is intended to partially replace the existing Basperstrasse and will provide access to the GERA's east control center and pumping station.
Requirements
- Material management
- Partial work on open waterways
- Short construction period