- Client: Canton of Valais, District 1 - Upper Valais, Mobility Department
- Site manager/reference person: Felix Abgottspon/ Canton of Valais
- Site manager: Celine Ludi
- Foreman: Diego Barberi
- Construction time: July 2024
- Construction costs: 0.40 million
Technical data:
- 585 m³ excavation/removal
- 510 m³ foundation 0/45
- 170 m of pipelines
- 5 inlet and inspection shafts
- 316 to Surfacing
- 42m concrete elements TRIC-BLOC
Project description:
A turning area was constructed along the route between Täsch and Zermatt so that a new permit procedure could be initiated at a later date. A bypass was created on the adjacent plot of land to ensure that the work could be carried out in parallel with the ongoing traffic.
Requirements:
- High volume of traffic
- Short construction time