Raron

GV drainage Neat bridge Steineji

  • Client: Department for National Roads Construction (DMRU-DNSB) 
  • Construction Manager / Reference Person: Ralph Tscherry 
  • Construction Foreman: Erhard Burgener 
  • Foreman: Paulo José De Almeida Oliveira  
  • Construction time: October 2021 - December 2021
  • Construction costs: 385'000.- 

Technical specifications:

  • 2'700 m³ excavation  
  • 450 m PP pipes DN/OD 500 
  • 530 m PP pipes DN/OD 630 
  • 6 Rehau AWA PE inspection chambers  
  • 1'200 m² formwork type 1 
  • 40 tons reinforcement   
  • 750 m³ NPK D AAR-resistant concrete 

Object description:

The existing drainage of the NEAT Steineji bridges runs into an infiltration basin, which is located in the project perimeter of the Steineji storage area and parking spaces project. For this reason, the existing infiltration basin must be relocated. New pipes and shafts will be used to drain the NRLA bridges into a temporary infiltration basin that is no longer located within the project perimeter of the A9 highway. 

Special requirements:

  • Increased accuracy of the gradient of the pipes  
  • Short construction time

Contact person

Paulo José De Almeida Oliveira

Foreman 

Erhard Burgener

Head of Civil Engineering
Member of the Executive Board

+41 79 744 68 16

+41 27 948 05 48

erhard.burgener@volken-group.ch