Herbriggen

Immediate measures Viaduct, Herbriggen

  • Client: Matterhorn Gotthard Railway
  • Site manager/reference person: Roland Walker, MGB
  • Foreman: Adem Salihi / Celine Ludi
  • Foreman: Alain Ritz
  • Construction period: July 2025 and August 2025
  • Construction costs: 600'000.--

Technical data:

  • 150m construction slope
  • 7 pieces underpinning Lehnenviadkut
  • 7 pieces of reinforcement foundations Lehnenviadkut
  • 150m new road surface
  • 100m construction of new DN 500 sewer system
  • 200m new block throw

Description of the project:

After the storm in July 2024, the roadway of the MGB was severely damaged. The existing leaning viaduct first had to be underpinned and then structurally reinforced. This was followed by the complete reconstruction of the roadway and the replacement of the damaged municipal sewer system. Finally, a new set of blocks was built to ensure better protection of the infrastructure.

Requirements:

  • Immediate measures
  • Work in the railroad area
  • No planning basis