Riederalp

Extension of snowmaking system

  • Client: Aletsch Bahnen AG
  • Construction Manager / Reference Person: Anton Franzen, Steve Krüger, Yannick Minnig
  • Construction Foreman: Jasin Ajeti
  • Foreman: Goran Aleksic
  • Construction time: June 2022 - October 2022
  • Construction costs: 420'000.-

 

Technical specifications:

  • Approx. 2.6 km trench excavation in loose rock and bedrock
  • Approx. 4.0 km cast iron pipes
  • Approx. 8.0 km cable protection pipes
  • 32 concrete shafts

 

Object description:

The Volken Group is expanding the snowmaking system on Riederalp to ensure snow reliability. A 2.6 km long trench will be excavated and provided with 32 concrete shafts. After filling the trench, the base for the slopes will be created.

 

Special requirements:

  • Mountain construction site
  • Short construction time
  • Logistics and transportation

Special features:

  • Material preparation for pipe coating with sieve bucket on site