- Client: Aletsch Bahnen AG
- Construction Manager / Reference Person: Anton Franzen, Steve Krüger, Yannick Minnig
- Construction Foreman: Jasin Ajeti
- Foreman: Goran Aleksic
- Construction time: June 2022 - October 2022
- Construction costs: 420'000.-
Technical specifications:
- Approx. 2.6 km trench excavation in loose rock and bedrock
- Approx. 4.0 km cast iron pipes
- Approx. 8.0 km cable protection pipes
- 32 concrete shafts
Object description:
The Volken Group is expanding the snowmaking system on Riederalp to ensure snow reliability. A 2.6 km long trench will be excavated and provided with 32 concrete shafts. After filling the trench, the base for the slopes will be created.
Special requirements:
- Mountain construction site
- Short construction time
- Logistics and transportation
Special features:
- Material preparation for pipe coating with sieve bucket on site