- Client: Canton Valais
- Construction Manager / Reference Person: Reto Gasser
- Construction Foreman: Antonio D'Onofrio
- Foreman: Diego Barberi
- Construction time: Nov./2021-Nov./2022
- Construction costs: 2 million
Technical specifications:
- 3000 m3 excavation
- 500 m3 demolition pavement
- 1700 m3 unbound mixtures
- 850 a. Asphalt
- 200 m2 formwork type 4.1
- 45 a.reinforcement
- 400 m3 concrete
Object description:
On the construction site of the H19 Brig - Furka pass road, section Mörel - Filet, the infrastructure lines and the pavement were constructed. The complete body was renewed from scratch.
Special requirements:
- Work during ongoing traffic (traffic lights)
- Difficulties due to railroad crossings (safety at work)
- Short construction time