Susten

New winery Leukersonne

  • Client:  Damian Seewer 
  • Construction Manager / Reference Person: Grand Adalbert Architekturbüro Leuk
  • Construction Foreman: D`Onofrio Antonio
  • Foreman: Pedro Oliveira 
  • Construction time: August 2019 until July 2020
  • Construction costs: 2.7 Mio

 

Technical specifications:

  • 4500 m3 excavation
  • 3000 m3 concrete
  • 350 to reinforcement
  • 1000 m2 brick walling
  • 4800 m2 wall formwork
  • 2600 m2 slab formwork
  • 150 m2 multi-layer slab of rock wool

 

Object description:

New building of the Leukersonne winery in Susten. The barrique cellar is in the basement. The ground floor and upper floor house the wine production, sales / tasting, warehouses and offices. The walls and ceilings of the basement are made of in-situ concrete. The walls and ceilings of the hall are made of in-situ concrete and partly of prefabricated concrete elements.

 

Special requirements:

  • Building in groundwater
  • Groundwater lowering (open dewatering)
  • White tank
  • Very short construction time
  • Large spans (industrial construction)
  • Combination of concrete prefabrication with in-situ concrete construction
  • Ceiling heights up to 9 metres
  • Complex buildings
  • Corona measures Pandemic


 